Garment costing to purchase order, step by step

Costing a garment and ordering it are one job in six steps. You set the price the style has to hit, cost it at the quantity you will order, plan its colours and sizes, then write the purchase order from those same numbers. Here is each step, with a worked example for an overshirt in two colours.

8 min readUpdated 24 November 2026

The six steps in short

  1. Set a target price. Start from the retail price the market will pay and work back to what one piece may cost to make.
  2. Build the bill of materials. List every fabric, trim and label, with how much one piece takes and the price at your order size.
  3. Add manufacturing. Put the factory's price per piece and its minimum order quantity (MOQ) next to the materials.
  4. Plan units by colour and size. Decide how many of each size you will make and check them against every MOQ and the collection's budget.
  5. Write the purchase order. Take the quantities from the plan and the unit price from the costing, and add delivery, shipping and payment terms.
  6. Approve, send and follow it. Lock the order, send it to the factory and track it until the goods arrive.

The rule that ties them together: the purchase order uses the same quantities and prices the style was costed with. When the two come from different files, margins change without anyone noticing.

Step 1: set a target price

Work backwards from the shelf. Say the overshirt should sell at €189 in shops.

  • Retailers often mark up wholesale by about 2.5, so the wholesale price (WSP) is about €189 ÷ 2.5 ≈ €75.
  • If your brand marks up landed cost by 2.5, the landed cost can be at most €75 ÷ 2.5 = €30.
  • Freight and duty add about 8% on this route, so the factory cost can be about €30 ÷ 1.08 ≈ €27.78.

Round it down and the target price is €27.50. That is the number design and production cost against. For more on markups and margins, see How to make a garment cost sheet.

Step 2: build the bill of materials

The bill of materials (BOM) lists what one piece is made of. Price each line at the quantity you will actually buy, since mills and trim suppliers charge more for small runs.

LineCalculationCost
Wool-blend twill1.9 m × €7.20€13.68
Buttons8 × €0.15€1.20
Main label and care label€0.50
Interlining and thread€0.55
Hangtag and polybag€0.30
Materials and components€16.23

Each colour gets its own BOM. An ecru overshirt with a different thread or button costs a little differently from the navy one.

Step 3: add manufacturing and check the MOQ

The factory quotes €11.50 per piece for cut, make and trim (CMT), with an MOQ of 300 pieces per style.

Materials €16.23 + manufacturing €11.50 = unit cost €27.73. That is about 101% of target, so the style is just over. Switching to an €0.08 button saves 8 × €0.07 = €0.56, which brings the unit cost to €27.17, or 99% of target.

This is the moment to fix the cost: before the purchase order, while a button or a fabric can still change.

CMT or full package? With CMT, the factory sews and you buy the fabric and trims yourself, so the purchase order to the factory carries only the CMT price. With a full-package (FOB) factory, the factory buys the materials and its price per piece covers everything. The BOM then becomes your check on whether that price is fair.

Step 4: plan units by colour and size

Plan the size breakdown per colour, for wholesale and your own retail.

ColourSMLXLTotal
Navy40808040240
Ecru30505030160
Total400

Now check every minimum: the factory's, the mill's and the budget.

  • Factory: 400 pieces is above the MOQ of 300 per style.
  • Fabric: navy needs 240 × 1.9 = 456 m and ecru 160 × 1.9 = 304 m. If the mill's minimum is 400 m per colour, ecru is under the MOQ. You can buy 400 m anyway and keep the rest, pay the mill's surcharge for a short run, or move units from navy to ecru.
  • Budget: 400 × €27.17 = €10,868 planned cost. Add it to the other styles and check the collection still fits its budget.

Step 5: write the purchase order

A purchase order is the moment a cost becomes a commitment. A garment purchase order should say:

  • PO number, date and a reference, such as SS27 drop 1
  • Buyer and vendor, with addresses and the vendor's email
  • Each style by colour and size, with quantities and totals
  • Unit price and currency per row, as the factory quoted it
  • Requested delivery date and where the goods go
  • Shipping terms, the Incoterm: EXW, FOB or DDP decide who pays freight and when the goods become yours
  • Payment terms, such as 30% deposit, 70% before shipment or Net 30
  • Notes to the factory: the approved sample, labelling and packing instructions

For the overshirt with a CMT factory, the order is 400 pieces × €11.50 = €4,600, plus separate orders for the twill and trims. The quantities come straight from the plan in step 4, and the price from step 3. If the factory invoices in another currency, write the order in its currency and check the total in your own.

Set the delivery date from the season's deadlines. When the goods have to be in the warehouse by a date, the order has to go out early enough for production and transport to fit before it.

Step 6: approve, send and follow it

Before the order goes out, check it once more against the costing: every row priced, quantities matching the plan, the vendor's email and the ship-to address filled in. Then lock it so nobody changes it by accident.

A typical order moves through Draft, Approved, Sent, In transit, Received and Closed. Keep the factory's replies, changed dates and files with the order itself, so the whole team sees the same story.

Once orders are sent, compare what has been ordered with the planned cost. That tells you how much of the season's budget is committed and how much is still a plan.

Where costing and purchase orders go wrong

  • The order and the cost sheet use different quantities. The style was costed at 1,000 pieces and ordered at 400.
  • An old price on the order. The factory raised its price after the cost sheet was made.
  • A missed MOQ. One colour falls under the mill's minimum and the surcharge eats the margin.
  • Currency. The factory quotes in dollars and the rate moves between costing and ordering.
  • Changes after sending. Someone edits the style, and nobody knows which version the factory is making.

Each of these comes from keeping the cost and the order in two places.

How Tr3e does it

Tr3e is a PLM for fashion teams and AI agents. Costing and purchase orders sit on the same product, so each step above uses the numbers from the one before.

A coat's cost, its manufacturing and its purchase order in Tr3e, in 36 seconds. Watch it on YouTube.
  1. Set the Target Price, RRP and WSP on the product.
  2. On each variant's Construction tab, add materials and components from the Library. Each line takes its Unit price from the item's recorded order, and its Unit count, such as 1.9 (m).
  3. On the Manufacturing tab, add the factory's process with its Price and Min. order. The variant's Unit cost shows against the target, such as 99% of target.
  4. Enter Retail and Wholesale units per size. The collection's Budget card shows the Planned cost, Projected revenue and Profit, and its Breakdown flags an Order under MOQ.
  5. From a manufacturing line's menu, choose Create Purchase Order. The order starts with the planned units as quantities and the variant's manufacturing price as the Unit price. Add the Shipping terms, Payment terms and Requested delivery date, and Switch to the vendor's currency if it differs.
  6. Review lists what stops the order being approved. Approve locks it, Download PDF gives you the file for the factory, and Mark as sent moves it on. The Budget card's Ordered figure then counts it.

Read more in How to cost every style and Purchase orders.

With an AI agent

Because the costing and the orders live in one PLM, an AI agent can work through the steps with you. In Tr3e you can ask the Agent, or Claude and ChatGPT through the Tr3e connector, to:

  • Add BOM lines from a sentence, such as the overshirt takes 1.9 m of the wool-blend twill.
  • List the styles whose unit cost is above their target price.
  • Show a product's cost breakdown, line by line.
  • Draft a purchase order from the planned units.

Approving and sending the order stay with a person in the app.

Next

Stuck on something? Book a 15-minute support call. Pick the topic when you book and we come ready.

Book a support callEmail us
Language
English
© 2026 Tr3e · Privacy · 5.0 on G2Your work is yours · Kept in the EU